How Long Does a Tub-to-Shower Conversion Take in Orlando?
For most homeowners in the Orlando area, a standard tub-to-shower conversion project typically takes between 3 and 7 working days to complete. This timeframe allows for proper demolition, installation, and finishing. However, the exact shower installation timeline can vary based on the complexity of the project, material choices, and any unforeseen issues. At D’Best Floorz & More, we pride ourselves on providing clear, realistic timelines for our Central Florida clients, ensuring a smooth and efficient renovation experience.
Factors That Influence Your Shower Installation Timeline
While a one-week turnaround is a great benchmark, several key factors can extend or shorten your project. Understanding these variables helps set realistic expectations for your renovation in cities like Winter Park, Kissimmee, or Orlando itself.
Scope and Complexity
The biggest variable is the scope of work. A simple conversion that fits within the existing footprint of your old tub is much faster than a project that involves:
- Relocating Plumbing: Moving the drain or showerhead requires more intensive plumbing work, potentially adding a day or more to the shower installation timeline.
- Expanding the Shower: If you’re knocking down a non-load-bearing wall to create a larger, walk-in shower, this adds significant framing and drywall work.
- Custom Features: Installing custom niches, benches, intricate tile patterns, or high-tech digital shower controls will naturally extend the installation process and affect the shower installation timeline.
Material Selection and Availability
The materials you choose play a crucial role in determining your shower installation timeline. Standard, in-stock ceramic or porcelain tiles are readily available. However, custom-ordered designer tiles, natural stone slabs, or special-order frameless glass doors can have lead times of several weeks, impacting the project’s start date. We help you source high-quality materials efficiently from our trusted Orlando-area suppliers to keep your project on track.
Unexpected Discoveries During Demolition
What lies beneath the old tub is always an unknown and can significantly impact the shower installation timeline. Once we remove the existing fixture, we might uncover issues that must be addressed before proceeding. Common discoveries in Florida homes include:
- Water Damage: Leaks from old plumbing can cause rot in the subfloor or wall studs, requiring repair.
- Mold or Mildew: Florida’s humidity can lead to mold growth behind walls, which requires professional remediation.
- Outdated Plumbing: We may find old, corroded pipes that don’t meet current Florida Building Code standards and need replacement.
A Detailed Day-by-Day Shower Installation Timeline
Here is a typical breakdown of what you can expect during your tub-to-shower conversion with D’Best Floorz & More. This schedule ensures each step is completed correctly without rushing critical stages like waterproofing.
- Day 1: Site Preparation & Demolition. Our team arrives and protects your home by laying down floor coverings and plastic sheeting. We then carefully disconnect the plumbing and demolish the old tub and surrounding tile walls. The area is cleaned of all debris to prepare for the next phase.
- Day 2: Plumbing & Electrical Rough-In. This is when our licensed plumbers and electricians (if needed) get to work. They will reconfigure the drain, install the new shower valve, and run any new wiring for features like recessed lighting or an exhaust fan.
- Day 3: Wall Preparation & Waterproofing. We install a durable, moisture-resistant cement backer board on the walls. This is followed by the most critical step: applying a liquid waterproofing membrane. We take extra care here, as proper waterproofing is essential for keeping the shower installation timeline on track and preventing future issues. This membrane needs time to cure properly.
- Day 4-5: Tile Installation. Once the waterproofing is fully cured, our expert tile setters begin their craft. This phase can take one to two days, depending on the size of the shower and the complexity of the tile pattern. The complexity of the tile pattern can directly affect the overall shower installation timeline.
- Day 6: Grouting, Fixture & Glass Installation. The tile is grouted, sealed, and cleaned. We then install the new fixtures, including the showerhead, handle, and any other accessories. If you’ve chosen a frameless glass door, it will be professionally measured and installed during this phase.
- Day 7: Final Touches & Cleanup. The final day involves applying silicone sealant, touching up any paint, performing a final inspection and water test, and conducting a thorough cleanup. We leave your new bathroom pristine and ready for you to enjoy. The final inspection ensures the completed project meets expectations and concludes the shower installation timeline.
Trust the Experts at D’Best Floorz & More

Navigating a tub-to-shower conversion requires expertise in plumbing, tiling, and local building codes. Attempting it as a DIY project can lead to costly mistakes and a much longer shower installation timeline. The D’Best Floorz & More team manages every detail, from initial design to final cleanup, ensuring your project is completed on time, on budget, and to the highest standards of quality for your Orlando or Cocoa Beach home.
Frequently Asked Questions
Do I need a permit for a tub-to-shower conversion in Orlando?
For a direct replacement without moving plumbing, a permit is typically not required in Orange or Seminole counties. However, if you are relocating plumbing or electrical lines, a permit and subsequent inspections are necessary. D’Best Floorz & More will handle the entire permitting process for you when required.
What is the biggest cause of delays in a project timeline?
The most common cause of delay is discovering significant water damage or mold after the old tub is removed, which can extend the shower installation timeline. Delays in the delivery of custom-ordered materials are the second most common factor.
Can I still live in my home during the renovation?
Absolutely. Our team works diligently to contain the work area to the specific bathroom, minimizing dust and disruption to the rest of your home. While that bathroom will be out of commission, the rest of your home remains perfectly livable.
Ready to transform your outdated bathroom into a modern, functional shower? Contact D’Best Floorz & More today for a free, no-obligation consultation! We serve the entire Greater Orlando area, including Winter Park and Kissimmee, and are ready to provide a detailed estimate and a personalized shower installation timeline for your project.